Charleston Under Construction

116 Meeting Street Renovation
116 Meeting St. 
Charleston

Project involved the renovation and restoration of a 10,000-square-foot historic fire station into an office building. Energy management efficiency upgrades were made, as well as structural repairs, building maintenance and new finishes.
Developer: Johnson Controls Inc. / City of Charleston, Charleston
Architect: Evans & Schmidt, Architects, Charleston
General contractor: NBM Construction Co. Inc, North Charleston
Engineer: ADC Engineering Inc., Hanahan, (structural); DWG Inc., Mount Pleasant, (mechanical / electrical).
Estimated completion date: November 2009
Estimated total cost of project: $1,750,000